Site visit on January 28 – Dry walls are going up Solar System installed – Metal roof end cap done

The metal roof was finished at the beginning of the month and it looks fantastic.

The work in the inside to place the crossed beams in the turret and the progress is showing the beauty of the design.

The Solar system was installed this week and inspection is in progress. There is another row going on the top of the array that was completed after this picture was taken.

The dry wall installation is going fast and furious, the inside of the house looks like a war zone. Here are some pictures showing the progress in the master bedroom, great room and pub areas: