Beautiful day at the lot today. We were able to view the 3 big trusses that are being put into place…..two in the great room and one for the main deck. Now the final portion of the roof framing will completed and ready for the roof. HVAC system also being completed. Windows waiting to be installed
We had a bit of a delay due to the truss arrival taking longer than expected plus the turret outer wall had to be rebuild. Everything now should move ahead rapidly as the push to get the house weather tight begins–that includes all exterior doors, exterior stucco and stone work, all windows and, of course the roof.


Wow wow wow…trusses are making the Ramos cathedral complete! Breathtaking!